Indigenisation Procedure

The Directorate is guided by the following procedure for indigenising an equipment or system:-

Vetting and Registration of Indent

1 week

Vendor Selection and Preparation of TE

1 week

IFA Concurrence, CFA Approval and Floating of TE

2 weeks

Submission of Quotations (technical & commercial bids)

3- 4 weeks (LTE- OTE)

Opening of Technical Bids & Technical Evaluation

3 weeks

Opening of Commercial Offers

2 weeks

Preparation of CST and Proposal

1 week

Proposal for Procurement/ Counter offer/ Scheduling of PNC and CFA approval

2 weeks

Brief for PNC, Notice for PNC and PNC Meetings

4 weeks

PNC Minutes and Signature

1 week

IFA Concurrence and CFA Approval for Developmental Proposal

2 weeks

Preparation and Despatch of Supply Order

1 week

Total

23-24 weeks

The directorate follows a two bid system (technical & commercial) of tendering processes. Approximate time frame involved in a two bid system is as follows :- 

             Activity

             Agencies involved

Formulation of Statement of Technical Requirements (SOTR)

Professional Directorates in NHQ

Vendor Identification

Professional Directorates & Directorate of Indigenisation (DOI)

Issue of Tender Enquiry to Vendors

DOI

Technical Evaluation of Tenders

DOI, Professional Directorate, User Directorate & Inspection Agency

Technical Negotiation with Vendor (if required)

DOI, Professional Directorate, User Directorate & Inspection Agency

Price Negotiation with Vendor (if required)

CFA, MOD/ IFA, DOI, Professional Directorate & User Directorate

Conclusion of Contract

DOI & Vendor

Approval of Drawing & QAP

DOI, Professional Directorate & Inspection Agency

Factory Acceptance Trials

DOI, Professional Directorate, User Directorate & Inspection Agency

User Trials

User/ User Directorate

Review of Design and Modification

DOI, Professional Directorate

Clearance for Bulk Production

DOI


Contact Address: The Officer-in-Charge
Indigenisation Unit (West)
Headquarters
Western Naval Command
C/o Fleet Mail Office
Mumbai-400001

Phone: 022-22751954
Fax: 022-22751954

Aircraft & Helicopters                          Ships