CHAPTER 5

MAZAGON DOCKS AND THE LEANDER FRIGATE PROJECT

PREAMBLE

    Until the 19th century, Mazagon Docks (MDL) used to build wooden hulled warships for the British Navy. In 1929, the 18 gun frigate "Tigris" and the 6-gun schooner "Shannon" were launched from MDL. As steel hulls gradually replaced wooden hulls, warship building in Bombay declined. The last warship to be built by MDL was the 80 gun ship "Madras", (renamed "Meanee"), in 1848.

Meanwhile the British Peninsular and Orient Company, (P&O) started a passenger ship service in 1842 from Suez to the Indian peninsula, initially to and from Calcutta and later to and from Bombay. This was the first of P&O's three main imperial routes - the others being to the Far East and Australia.

In 1914, P&O acquired the British India Steam Navigation Company (BISN) which was managed by Mackinnon Machenzie of Calcutta. This `P&O Group' became the main operator for India's coastal passenger traffic. Its services linked India with the Persian Gulf, the Far East and East and South Africa. Mazagon Docks Ltd (MDL) at Bombay and Garden Reach Workshops (GRW) at Calcutta were developed by the P&O Group to maintain their ships in Indian waters. For many years, the P&O Group held a controlling interest in the Mogul Line. After Independence, from the early 1950's onwards, MDL, GRW and the other small construction yards started meeting the nation's need for small vessels and harbour craft.

During the Second World War, an urgent need had arisen to build merchant ships in India to replace Britain's wartime losses. The Scindia Steam Navigation company was given a site at Visakhapatnam. The first Indian built merchant ship was launched in 1948. In due course this yard was taken over by the Government and renamed Hindustan Shipyard Limited (HSL).

Go on top

ACQUISITION OF MDL AND GRW

In 1956, the P&O group offered to sell MDL to the Government of India. The Planning Commission's reaction to this offer in July 1956 was "the demand for ships of 4000 GRT and below, especially for new ships, and the demand for old harbour craft are so small that it would not be advantageous for Government to consider taking over Mazagon Docks merely for the construction of smaller vessels" (Material from MDL).

In 1957, Mr Krishna Menon became the Defence Minister. He was determined that India should be self reliant for its basic defence requirements like tanks, warships and aircraft. It was clear that HSL would be overloaded if given the task of warship building and that only MDL and/or GRW could build large warships. He appointed a committee to look into MDL's capabilities and limitations, with a view to build frigate sized warships in India.

After protracted negotiations under Mr Krishna Menon's forceful leadership, the Government of India in a package deal purchased MDL and GRW for 12.1 million pounds (approx Rs. 3.85 crores) on 19 April 1960. The package deal provided for part of the payment to be adjusted towards repairs of P&O Group ships after take over.

Go on top

MODERNISATION OF MDL

In November 1960, Government approved in principle that three Leander class frigates should be built in India. Soon thereafter, MDL submitted a preliminary report on the facilities required to modernise MDL for building frigates.

MDL was a 35 acre site, needing extensive modernisation and expansion before it could build frigates. On its northern boundary was Kasara Basin, a low lying, neglected wharf belonging to the Bombay Port Trust, and occupied mostly by fishing vessels which rested on mud at low water. On MDL's southern boundary was the jeep assembly plant of Mahindra and Mahindra, on lease from the P&O Group since 1949 until 1962. Under Mr Krishna Menon's nudging, Mahindras vacated the South Yard in 1962 and the Bombay Port Trust leased Kasara Basin to MDL in 1963.

MDL had two medium size dry docks - one for seagoing ships and one for harbour craft - and a number of slipways which could accommodate coasters and lighters up to 150 tons. Though MDL's primary activity was ship repair, it did not have any alongside berths. Repairs had perforce to be undertaken in Bombay Port Trust berths.

After receiving MDL's preliminary report on its requirement for additional facilities, the Government retained the British firm of Shri Alexander Gibbs and Partners (who were also consultants for the Expansion Scheme of Bombay Naval Dockyard) to advise and prepare plans for expanding MDL's facilities, both for ship repair and ship construction. Keeping in view the imminent construction of frigates, their major recommendations were:

By end 1963, the plan for impounding the Kasara Basin had been approved and the construction had started of the 450 foot slipway in the South Yard. however, since the collaboration for the Frigate Project was still under discussion, the final layout of the yard and the siting of shops were kept pending the finalisation of the frigate building contract.

By 1968 most of the civil works for MDL's modernisation had been completed. The Kasara Basin was flooded on 23 Aug 1968 in time for NILGIRI, the first frigate launched on 23 October 1968, to be towed into the new impounded wet basin and secured alongside for fitting out.

Go on top

GOA SHIPYARD

Immediately after Goa was liberated, the Government of India directed MDL to take over responsibility for the Estaleiros Navais de Goa (Goa Shipyard) on 19 December 1961. In April 1962, Goa Shipyard Ltd (GSL) was leased to MDL. This lease was terminated on 30 September 1967 and GSL made a subsidiary of MDL. GSL undertook ship repair, built barges and fishing trawlers to start with and started building warships in the 1980's.

MDL STARTS WARSHIP REFITS

From 1963 onwards, the Navy started off-loading its ships to MDL for major refits, involving overhauls of boilers and extensive hull renewal. By this time, the first Warship Overseeing Teams had been appointed.

SELECTION OF SHIPBUILDERS FOR COLLABORATION

On 25 November 1960, Government approved in principle that three Leander Class Frigates should be built in India. MDL submitted a preliminary report on the civil works, machinery and equipment required to undertake this project. At this stage, Government deputed a team of three senior naval officers to Britain to discuss with the Admiralty, the collaborating shipbuilders and the armament suppliers, the steps to be taken for building the first modern major war vessel in India. The team was to submit a project report and recommendations on the arrangements to be made by NHQ and by MDL to execute the project expeditiously and economically. The three officers were Captain (L) KR Ramnath, the Director of Stores Production (Navy), Captain (E) BP Sinha, the Director of Naval Construction and Captain (E) CL Bhandari, the Managing Director of MDL. This teams discussions and recommendations laid the foundation of the subsequent negotiations which culminated in 1964.

The overall framework of collaboration emerged as follows:

Go on top

Summary of the Team's Report and Recommendations

Go on top

VICKERS/YARROW REPORT ON FACILITIES REQUIRED IN MDL

From the British side, a team of officials from Messrs Vickers Ltd and Messrs Yarrow Ltd conducted an extensive survey of the facilities available in India and produced, in 1962, their proposal to build Leander class frigates in Mazagon Docks.

FINAL TECHNICAL - ECONOMIC ASSESSMENT OF FRIGATE DESIGN OPTIONS

In mid 1962, a delegation was sent to make a final technical-economic assessment of the Vickers/Yarrow proposal vis-a-vis collaboration proposals subsequently received from Sweden and Holland. Rear Admiral (later Admiral) SM Nanda, who was Deputy Chief of the Naval Staff, led this delegation.

Admiral Nanda recalls:

Go on top

THE CHOICE OF THE FSA 34 LEANDER DESIGN AND
FINALISATION OF AGREEMENTS IN 1964

In their earlier discussions since 1961, it had been agreed that the Admiralty would give India the FSA 29 Leander design which had already been introduced in the Royal Navy. During the intervening years, whilst discussions and negotiations were going on, the Admiralty had decided to introduce for their Navy, a modified design called the "FSA-34". In this design, the beam was broader by 2 feet (0.61m). It incorporated the latest equipment modifications and made provision for incorporating future modifications.

During the Defence Minister's visit to Britain in November 1964, the discussions on the Frigate Project covered three major aspects.

A credit agreement was signed under which the British Government agreed to provide a special loan of 4.7 million pounds to meet the external costs, during the first four years of the programme, for expansion of MDL's facilities to construct three Leander Class Frigates.

By end 1964, all the major aspects of the collaboration had been finalised. In addition to the technical aid fees, an annual amount 40,000 pounds was to be paid for the Indian Frigate Project Organisation in Newcastle, whose function was to liaise with the Lead Yard, Yarrow (Shipbuilders), who were to provide the basic working drawings for the construction of the first Leander in India.

The Memorandum of Agreement for the Leander Frigate Project, known as the "Blue Book", was signed on 22 December 1964, between the Government of India and Vickers Yarrow. The Blue Book covered three aspects:-

    This Memorandum became operative on 27 January 1965, when a parallel agreement was signed between the Government of India and the Ministry of Defence (Navy) UK. The agreement authorised Vickers/Yarrow to operate the agreements in the Blue Book. The parallel agreement related to the payment of design fees of

400,000 pounds to the Ministry of Defence (Navy) UK for the training of Indian personnel in Royal Navy Dockyards, the supply of Admiralty pattern items of stores and equipment, the scrutiny of quotations and the inspection of material and equipment on behalf of the Government of India.

The Government of India then placed an order on MDL for the construction of the first frigate. The salient features of the agreement with the MDL were:-

Go on top

POSITIONING OF TOP MANAGEMENT

After the frigate contract was signed, the Government appointed to MDL the two key persons who had been closely associated with the Frigate Project during the negotiations. Mr HC Sarin ICS was appointed Chairman MDL on 7 November 1964, in addition to his duties at Secretary Defence Production in the Ministry of Defence. Rear Admiral (later Admiral) SM Nanda, who had been associated with the project as Chief of Material in 1961/62 and as Deputy Chief of the Naval Staff in 1963/64, was appointed Managing Director MDL on 14 December 1964. Mr Sarin remained Chairman MDL for five years till 28 Sep 1969. Rear Admiral Nanda handed over to Rear Admiral BA Samson on 3 May 1966, who later also became Chairman MDL until he retired on 15 May 1973. This close association of the Ministry of Defence Production, NHQ and MDL and the long tenures of the top management were to prove invaluable for the timely and successful resolution of innumerable teething problems of the Frigate Project.

THE PROBLEMS TO BE OVERCOME

Whilst Naval Headquarters had the satisfaction of having signed for the latest available Leander design, the FSA 34, the first British Leander of the FSA 34 series was not expected to be commissioned in the Royal Navy before 1969. Expectedly, there was scepticism of whether MDL would be able to build in India a sophisticated warship as modern as what the British Navy would have.

The sceptics, both in India and abroad, had sound reasons. Those in Britain who had been building warships were well aware of the complexity of coordinating practically every aspect of naval architecture, marine engineering, electrical and electronic technologies. Those in India knew that the MDL faced several formidable challenges:

Go on top

DELAYS IN CONSTRUCTION OF MDL FACILITIES

The basic facilities required to begin the Frigate Project started to fall behind from the outset. As mentioned earlier, the Government, while approving MDL's expansion scheme, had advised postponing the siting of the Plater & Assembly Shop (P&A Shop) until the type of warship to be built and the collaborators had been finalised. This delayed the construction of the P&A Shop. The civil works of the P&A Shop were completed only in 1967, well after the keel of the first frigate had been laid. The installation of machinery and the laying of the services in the P&A Shop continued throughout 1967 and 1968, until the first frigate was launched.

The construction of slipways in the South Yard was also delayed due to the unexpected soil conditions. The resultant re-planning upset the expansion schedule, which in turn delayed the installation of the cranes. At every step, there was some unforeseen difficulty or the other, resulting in revision of plans and compelling improvisation and innovation.

Go on top

TRAINING IN BRITAIN FOR CONSTRUCTING FRIGATES

Vickers made the generous gesture of starting the training of Indian personnel from the Navy and from MDL even before the contract was signed in October 1964.

The skills required for warship building were vastly different to those for construction of merchant ships and totally different to those needed for ship repairs. There were over 35 warship building trades as against only 10 merchant shipbuilding trades. A complete re-orientation of training was therefore necessary.

MDL deputed a number of its senior and junior officers for training in the shipyards of Vickers and Yarrow, for periods ranging from six months to two years. A small body of about 150 workmen of all categories were also deputed to these shipyards to observe at first hand the techniques for building and fitting-out. When these officers and men returned to MDL, they in turn trained other officers and men while actually building the first frigate.

Go on top

TRAINING IN BRITAIN IN SHIP DESIGN.

Two officers, Lt Cdr (later Commodore) SC Bose (a marine engineer) and Lt (later Captain) Mohan Ram, (a naval constructor) were sent to the British Navy's Director General Ship Design Office at Bath to study the design philosophy of the Leander class frigates.

Go on top

CONTROLLER INDIAN FRIGATE PROJECT ORGANISATION(CONIFPO) IN UK

To implement the Frigate Project, a small Frigate Cell consisting of a British Naval Architect, with a team of draughtsmen and others from MDL, was set up in 1966, initially in Vickers at Newcastle, although Yarrow, the Lead Yard, was building the first British FSA 34 Leander in Glasgow. Details were fed from Glasgow to Newcastle, where the basic drawings were to be made and then forwarded to India in accordance with a predeterminded schedule.

MDL had its own representative, Commodore (later Rear Admiral) HK Kapadia designated Controller Indian Frigate Project Organisation (CONIFPO,) at Newcastle. He had a team of technical and financial managers to liaise with the Admiralty, with Vickers and with Yarrow and negotiate purchase of equipment in Britain and to ensure its timely despatch to MDL in Bombay.

FRIGATE CELL/SECTION IN MDL

The set-up in MDL was also re-organised to cater to the Frigate Project. In 1966, a Frigate Cell was established with those who had returned from UK after training. Commander(E) YP Batra, as Planning Manager, Commander(C) AN Thukral, as Officer-in-Charge Frigate (Hull), Shri J Kharas, as Officer-in-Charge Frigate (Electrical), Shri Dom Menezes, as Officer-in-Charge Frigate (Engineering). This Cell was later re-designated 'Frigate Section' and was headed by Commander (E) (later Vice Admiral) BR Choudhury, Commander (L) (later Captain) S Prabhala, Commander (E) KM Acharya and Commander (E) T Deva in succession.

The Frigate Section, among other things, was responsible for producing from the basic drawings received from Vickers, the detailed working drawings required for practical implementation in the shops and on the slipways.

Go on top

DELAYS IN STARTING CONSTRUCTION

After a ships hull has been fully fabricated, each compartment in the ship is marked off from detailed drawings to assist the location of equipment, as also the exact positioning of electrical cables, piping systems, ventilation systems, etc. After locating the position of all these systems in each and every compartment and after making minor adjustments wherever necessary, work begins to instal various systems and equipment.

For the NILGIRI, MDL had to manufacture and install 20 miles of ferrous and non-ferrous piping of varying sizes serving 61 systems. 180 miles of electrical cabling of different types and sizes had to be installed. Except the main machinery compartments, which were fitted with a forced air supply and exhaust systems, all compartments in the ship had to be provided with air conditioning. The length of air trunking involved was approximately two miles. Specialised equipment had to be installed in a pre-determinded sequence. This required detailed coordination. If one item or system was delayed, the sequence of the entire fitting out process was delayed.

By the end of 1966 it became abundantly clear that the information and drawings from the Frigate Cell in Newcastle were coming out far too late and without the detailed information that was essential to order the many hundreds and thousands of items of various kinds in adequate time to ensure that they were available when required. This began to seriously affect NILGIRI's construction schedule. MDL began falling back at the very outset and by mid 1967 was almost two years behind schedule in respect of information and drawings from the Frigate Cell in Newcastle. All MDL's complaints and appeals seemed to fall on deaf ears. By end June 1967 the situation had become alarming.

Go on top

AVAILABILITY OF MATERIAL REQUIRED FOR CONSTRUCTING FRIGATES

One of the major bottlenecks in the Frigate Project was the availability of material, machinery and equipment of the required standard and quality, at the right time and in the right quantities. In the end 1960's, India's industrial base was not sufficiently developed to produce the specialised equipment and material required in shipbuilding, much less in warship building. One had to rely largely on imports. Even in the case of imports, there was the problem of ordering long lead items like weapons, main propulsion and auxiliary machinery as much as three years in advance and then have it inspected, packed and shipped to MDL.

As for the steel plates, three types were required namely mild steel, 'B' quality steel and 'A' quality super-grip plates By the end of 1965 the Rourkela Division of Hindustan Steel had developed only mild steel. This was used in the first frigate, amounting to some 65%. The rest had to be imported. Action was later initiated to manufacture 'B' quality steel and, after considerable effort, Rourkela succeeded in 1967. The stringent tests carried out on the trial plates proved to be highly satisfactory. In addition, Hindustan Steel had also developed steel plates to specification BSS 1501-151. These plates were used for special purposes. By the time the second frigate was being built, 95% of the steel plate requirements were met indigenously.

Go on top

CREATION OF DIRECTORATE OF LEANDER PROJECT IN NHQ

In 1968, Government sanctioned the new Directorate of Leander Project in NHQ to handle all aspects of design, to coordinate with Vickers and with Yarrow, to approve drawings and generally manage all the technical activity of the Leander Project from the NHQ end.

Go on top

THE FIRST FRIGATE - INS NILGIRI

INS NILGIRI's keel was formally laid on 15 October 1966. Inspite of all the problems, MDL bravely invited the Prime Minister to launch the NILGIRI on 23 October 1968-barely two months after the Kasara Basin was expected to be impounded.

Then MDL encountered a problem of another kind - Labour.

Go on top

FITTING OUT AND TRIALS

After a ship reaches an advanced stage of fitting-out, the equipment is tried and tested in `Basin Trials'. Each and every system in the ship is thoroughly tested to the satisfaction of the Navy's Warship Overseeing Team and any adjustments required are undertaken.

After that the ship is put to sea for 'Builder's Sea Trials', also known as 'Contractor's Sea Trials'. On completion of each trial, specific items of machinery are `opened up' for inspection, defects put right and again tried at sea. This process goes on until everything is satisfactory, after which the machinery is finally `boxed up'.

The Final Acceptance Trials extend over a nine month period. Tests are designed to withstand severe conditions, more rigorous than what the ship would normally experience at sea. After successful Acceptance Trials, the ship is handed over to the Navy.

The time taken from keel laying to launching of the first frigate came to two years, but for the fitting-out of the ship, the basin trials, the sea trials and up to the commissioning, the period extended to another 3 years and 8 months. In warship building, the fitting out is always time consuming. Nevertheless, a total 5 1/2 years from keel-lying to delivery was long, because of the teething problems.

COMMISSIONING

INS NILGIRI was commissioned on 3 June 1972 by Mrs Indira Gandhi, the Prime Minister of India. There were 35 Leanders afloat in other Navies at the time. NILGIRI was the 36th Leander. Apart from the British Navy, the Dutch, Australian and New Zealand Navies also had Leander design frigates.

Go on top

CHANGES IN SENSORS AND WEAPONS TO IMPROVE CAPABILITY

In the first instance, the Government had ordered only one frigate to be constructed. There was delay in placing the order for the second and third frigates because India was going through a foreign exchange crisis. The special credit of 4.7 million pounds could not be stretched to include the foreign exchange requirements beyond the first frigate. The rupee was devalued in June 1966 and the Government had to resort to annual plans from 1966 to 1969. Eventually in early 1968, Government placed an order on MDL to build two more frigates. This was six months later than the original plan for commencement of the second Leander, which eventually began in May 1968.

Receiving orders piece-meal was one of the handicaps that MDL had to accept. The advantage of MDL ordering economic quantities on its suppliers had to be sacrificed. The Dutch who built the Leanders in their yards at Amsterdam and Flushing, constructed six ships of the series almost simultaneously, all of which were commissioned between March 1967 and May 1968.

Naval Headquarters took advantage of the delay in NILGIRI to improve the sensors and the AIO for the subsequent Leanders.

There were several schools of thought at that time about the desirability of changing equipment from ship to ship. MDL felt that by avoiding changes, ships could be delivered quicker and cheaper. NHQ felt that if we continued to build a series of ships with obsolescent sensors, weapons and equipment, they would not meet the staff requirement. And from the view point of indigenisation, it was not cost effective to indigenise obsolescent technology.

Go on top

INTERACTION WITH THE NETHERLAND WARSHIP DESIGN BUREAU (NEVESBU)

Two officers were sent to NEVESBU. Commander (L) (later Rear Admiral) JJ Baxi was one of them. He recalls:-

Eventually, HIMGIRI and the subsequent Leanders were fitted with the following Signaal equipment:

Similarly the British Sonar 184 was replaced by the later Sonar 184 M.

Go on top

THE SECOND FRIGATE - INS HIMGIRI

HIMGIRI's keel was laid on 4 November 1968. She was launched on 6 May 1970. MDL had been able to reduce the time between keel laying and launch from 25 months to 18 months. The fitting-out however was considerably delayed due to the late arrival of major items, both from abroad and India.

The machinery installation was completed in December 1973, Basin Trials were successfully completed in January 1974 and the Contractor's Sea Trials commenced on 6 April 1974. At the preliminary full power trials, the temperature of the gear box bearings was found to be rising above acceptable limits. The gear box was the first to have been made in India to the Swiss MAAG design. After detailed examination, Naval Headquarters, in consultation with Swiss designers, decided to modify the bearings and check the alignment of the turbines. The Repeat Contractor's Sea Trials in September 1974 were successful, and HIMGIRI commissioned on 23 November 1974.

On the plus side, HIMGIRI got better radars, sonars, AIO and fire control equipment and two Seacat guided missile launchers. Design changes were also made in the communication systems and the layout of mess decks to improve habitability in tropical conditions.

Captain Prabhala recalls:-

Go on top

THE THIRD FRIGATE - INS UDAYGIRI

Since orders for the second and third frigates had been received together, MDL seized the opportunity to build them faster than the first frigate. The fabrication work on the third frigate, scheduled to commence in January 1970, started in April 1970 due to late receipt of steel from Hindustan Steel Ltd.

In 1969-70 there had been an acute shortage of steel. MDL had been able to carry on production without serious dislocation as its earlier orders for steel had materialised. By 1970-71 however, the fall in steel production adversely affected MDL's work. The interval between keel laying and launching increased to 25 months. The main machinery which should have arrived at the time of the ship's launching in October 1972, was actually received in May 1974, thereby further delaying the ships commissioning till 18 February 1976.

Go on top

THE FOURTH FRIGATE - INS DUNAGIRI

The fourth Leander was launched on 9 March 1974. She was on the slipway for only 14 months as compared to 18 to 25 months for the second and third frigates respectively. Fitting out was affected by delays in receipt of indigenous as well as imported equipment. The main engines and gear boxes were received in May 1975. Basin trials were carried out in October 1976 and sea trials completed satisfactorily in November/December, 1976. The final inspection of hull, weapons, radio compartments and systems was completed in early 1977. DUNAGIRI commissioned on 5 May 1977.

The time between keel laying and launching had been reduced to 14 months. The time from launching to delivery had been reduced to 38 months - the shortest period yet achieved. Nevertheless, the total of 58 months from start of production was still too long by world standards. On the other hand, the range of equipment being indigenously produced for the first time by Indian industry was impressive: main boilers, main turbines, main gearing, main circulators, turbines for turbo alternators, diesel alternators, stern tube bushes, heat exchangers, radar and fire control equipment, data processing computers, air conditioning and refrigeration machinery, broadcast equipment, telephone and teleprinter equipment, main and auxiliary switch boards, complex system valves, fire detection sensors and a host of other minor equipment. By the time the fourth Leander had been built, considerable confidence had built up at all levels.

Go on top

IMPROVEMENTS OF ANTI SUBMARINE
CAPABILITY IN THE FIFTH AND SIXTH LEANDERS

In 1972 and 1973, as operating experience was gained with the NILGIRI and the Seaking anti submarine, dunking sonar helicopters, and in view of the continuing acquisition by Pakistan of modern submarines from France, it became clear that future Leanders would require greater anti submarine capability.

Naval Headquarters initiated studies in early 1973 to improve the anti submarine capability of the 5th and 6th Leanders. These changes crystallised in mid 1973. The major changes envisaged embarking the heavy Seaking helicopter and improving the anti submarine sonars and weapons.

Seaking Helicopter

In 1966, the Canadian Navy had pioneered the operation of a Seaking helicopter from the deck of a frigate. This entailed designing a Bear Trap Haul-down and Traversing system for moving the heavy helicopter on the small flight deck, providing a large hangar and strengthening the flight deck to bear the weight of a heavy helicopter. All these changes would affect the ships overall design, stability and seakeeping qualities.

To meet the conflicting requirement of a large hangar and a long clear flight deck, the hangar would have to be telescopic. Extra flight deck space aft could only be made available by removing the anti submarine Mortar and the Variable Depth Sonar wells.

Anti Submarine Sonars and Weapons.

The changes envisaged in the ships sonars and anti submarine weapons were:-

All the above design modifications and changes were discussed with individual equipment suppliers in Canada, Sweden, Britain and Italy in 1974. By 1975, all the changes had been finalised.

Go on top

Changes in Design

Go on top

THE FIFTH FRIGATE - INS TARAGIRI

These design changes delayed the commencement of construction, which should have started immediately after the launching of the fourth frigate. Production could commence only in April 1975. The keel was laid six months later and the ship was launched on 25 October 1976. Thereafter there was a major setback in fitting-out because of a delay of one year in receipt of the main engines. This created its own chain of delays. Contractor's Sea Trials commenced in April 1979. During trials, internal vibrations were observed in the main turbines. After the defects were rectified, repeat sea trials were satisfactorily completed in December 1979, and TARAGIRI was commissioned on 16 May 1980. Whilst the time from keel laying to launch had been only 12 months, the least period so far, the time taken from launching to commissioning was 43 months, much more than the time taken for any of its predecessors.

THE SIXTH FRIGATE - INS VINDHYAGIRI

VINDHYAGIRI was identical with TARAGIRI. Construction commenced on 5 July 1976. Her keel was laid on 5 November 1976, and she was launched on 12 November 1977 after a period of 12 months, the same time as was taken for the TARAGIRI. She commissioned on 8 July 1981, having taken 44 months from launch to delivery.

Go on top

THE INDIGENISATION OF LEANDER CLASS FRIGATES

In 1955, the Directorate of Stores Production (Navy) had been set up under Naval Headquarters. In December 1956, it was transferred to the Ministry of Defence under the Controller General of Defence Production as part of the Director General Inspection. Its designation was changed to Directorate of Development and Inspection (Marine Stores), DDI(MS). By 1965, it had been able to:-

The major handicaps that had been encountered were:-

By the time the Leander Project got under way in the mid 1960's, the field work of the preceding ten years proved to be invaluable for the indigenisation of Leander equipment.

As part of the Leander Frigate Project, a Study Group on Indigenisation was set up in Delhi to function in close consultation with MDL for locating capacity for indigenous manufacture. In 1966, Commander (later Admiral) JG Nadkarni, was appointed as Officer on Special Duty in the Department of Defence Production.

Go on top

REMINISCENCES OF THE LEANDER FRIGATE PROJECT

Captain Prabhala, later Chairman and Managing Director of Bharat Electronics Ltd, recalls:-

Rear Admiral Baxi, also later Chairman and Managing Director of Bharat Electronics Ltd, recalls:-

Go on top

THE LEANDER FRIGATE PROJECT IN RETROSPECT

The Leander Frigate Project, which commenced with the construction of the NILGIRI on 23 October 1966, completed with the commissioning of the VINDHYAGIRI on 8 July 1981. During these fifteen years, six frigates were delivered, an average of 30 months per ship. By the time of the 6th Leander, the indigenous content of bought out equipment had risen to 70%.

From every point of view, the Leander Frigate Project was a monumental achievement. The boldness of the naval decision makers, the enthusiasm, perseverance and dedication of the implementers in MDL, in the Ministry of Defence Production and in the Navy, the assistance by the British Admiralty, by the British shipbuilding collaborators, Vickers and Yarrow, by the Dutch Design Bureau NEVESBU, all of these were essential ingredients of success. Most valuable of all was the close and informal interaction between personages as high as the Secretary Defence Production and his team in the Ministry of Defence and Defence Finance with the bright young naval officers of the Leander Project. The elders trusted the youngsters to do what they thought was best. Likewise, the astounding success of indigenisation was a direct result of the high powered Indigenisation Committee's free, frank and helpful interaction with Indian Industry through DWP and DPI(N).

The enormous self confidence gained in this project by the Navy's weapon planners, the naval architects and the shipbuilder laid the foundation for the more audaciously designed warships that later emerged from Indian shipyards.

The table below shows the gradual diversification in combat systems from the first Leander to the sixth Leander. Equally significant changes were effected in the engineering and electrical machinery of these six ships.

  NILGIRI (First Leander HIMGIRI, UDAYGIRI DUNAGIRI 2nd, 3rd and 4th Leanders) TARAGIRI VINDHYAGIRI(5th and 6th Leanders)
Surface to Air Missile Launchers and Fire Control Fire Control British Dutch Dutch
Gun Mounting British Dutch Dutch
Ship Launched Anti-Submarine Torpedoes     Italian
Anti Submarine Weapon British British Swedish
Anti Submarine Helicopter French Alouette with British Torpedoes Indian Alouette with British Torpedoes British SEAKING with Italian Torpedoes
Close Range AA Guns 20 MM Oerlikon (ex stock) 20 MM Oerlikon (ex stock) 20 MM Oerlikon (ex stock)
Radars Dutch Dutch British
Sonars British British British and French
Action Information system British Dutch Dutch
Electronic Warfare British British Italian

Go on top